A personal blog of our experiences in building a two story 16x26 house by ourselves in Alaska
Monday, July 18, 2011
Make a Donation
Breaking down the costs.
It quickly became apparent though, that this was one more project that will have to stay on the back burner as we just have too many things to finish in order to move in before winter comes.
We have a list of goals and expenses on our wall in the cabin to help us plan out what our upcoming goals are and what the anticiapted cost is for those goals.
Project costs
Upstairs insulation $2,500
Upstairs sheetrock, mudding and taping $1,000
Upstairs Painting $200
Finish crawl space with gravel, insulation and skirting $3,000
Carpeting upstairs $600
Get a queen size bed $1500
Finish the woodstove surround $100
Finish the stairs and railing $200
Composting toilet $400
Total $9,300
Other costs beyond this
Having a well drilled and pump installed at least $3,000
Installing a leach field for gray water about $500
Building an addition for a bathroom $?
Siding $?
I am also taking classes to get my Masters Degree in Special Education. Getting financial aide for college is helping us with our house building. But, sad to say, it doesn't look like running water is going to be an option for a little while longer. Maybe next year. That said, there is a link above for you to be able to make a donation to us to help us with our dream. If you can't afford to make a donation, please feel free to click some ads and browse for a while. That earns us a little $ too.
Thanks!
Tuesday, May 31, 2011
Color me happy!






Thursday, March 3, 2011
Getting Warmer......
Once we had saved it up, we contacted a different local contractor who was unwilling to do the job until the summer because the expensive equipment in their long trailer had nearly been lost before on roads much better than ours. So, they didn't want to take that risk.
During
So, we contacted a couple of other contractors, including Hillside and only heard back from them. I have no idea why people didn't want the work. Regardless, Mike Basargin and his co-worker Ivan came up on Tuesday around Noon and worked until about 9PM. This was the first time that we hired anyone to do work on our house. It was hard to be patient and stay out of the way as they worked.

Scraping the studs
As soon as we heard the generator stop, we leapt from the loveseat in the cabin and helped them clean up as they scraped the extra insluation off the studs.

Cleaning Up
The Finished Product
The woodstove has been put back in place and the plastic sheathing has been removed from the doors and windows.
The next step is to begin sheetrocking. The "lid" and the entryway walls are the first priority for that project.
We decided that insulating the first floor fully would allow us to then move forward and take the next steps and make it more of a home. We had contemplated applying 2" of spray foam throughout the house (because that was what we could afford) but realized that we wouldn't really be able to do much after that except wait until we had the money to get more insulation.
So, as of March 3rd, that is where we are. :)
Wednesday, December 29, 2010
Planning and saving
Saturday, October 9, 2010
It's Electrictrifying!
THE FIRST LIGHT SWITCH!
And.....IT WORKS!!!!!
It's official. We now have electricity!